Would you like to see 4 invoices (totalling £24,239.39) for pre construction work on the Saughall Massie fire station project?

Would you like to see 4 invoices (totalling £24,239.39) for pre construction work on the Saughall Massie fire station project?

Would you like to see 4 invoices (totalling £24,239.39) for pre construction work on the Saughall Massie fire station project?

                                               

This continues from an earlier post headlined Would you like to see 2 invoices (totalling £153,250.61) for pre construction work on the Saughall Massie fire station project?

Below are 4 invoices Wates Construction Limited to Merseyside Fire and Rescue Service for work to do with the Saughall Massie pre-construction agreement. I requested these invoices as part of the 2016-17 audit and they arrived through the post today.

The invoices spell it as Saughall Massey rather than Saughall Massie. The invoices are dated March 2016 (for £4,696.99), April 2016 (for £4,547.96), May 2016 (for £12,086.83) and August 2016 (for £2,907.61). Total spending was £24,239.39 (all amounts in this paragraph include VAT).

I also received a copy of the pre-construction service agreement between Merseyside Fire and Rescue Authority and Wates Construction Ltd. As it’s around 45 pages long I don’t have the time just now to scan it in or publish it today.

However, the contract is based on JCT’s Pre-Construction Services Agreement (General Contractor) (PCSA) 2011 contract with some modifications from the original template.

The contract is also with Todd & Ledson LLP. I haven’t requested invoices for the 2016-17 financial year relating to Todd & Ledson LLP and the Saughall Massie project as there is only one that could relate to this for £2,500 dated 25.4.16 (although it is possible this invoice relates to completely different work as it is just described as services).

Wates Construction Ltd invoice March 2016 Merseyside Fire and Rescue Service resized
Wates Construction Ltd invoice March 2016 Merseyside Fire and Rescue Service resized
Wates Construction Ltd invoice April 2016 Merseyside Fire and Rescue Service resized
Wates Construction Ltd invoice April 2016 Merseyside Fire and Rescue Service resized
Wates Construction Ltd invoice May 2016 Merseyside Fire and Rescue Service resized
Wates Construction Ltd invoice May 2016 Merseyside Fire and Rescue Service resized
Wates Construction Ltd invoice August 2016 Merseyside Fire and Rescue Service resized
Wates Construction Ltd invoice August 2016 Merseyside Fire and Rescue Service resized

I wrote up about the site visit connected to this planning application yesterday.

Wirral Council’s Planning Committee will be deciding on the revised planning application (APP/17/00306) at a public meeting starting at 6.00 pm on Thursday 20th July 2017 in the Civic Hall, Wallasey Town Hall, Brighton Street, Seacombe, CH44 8ED.

If you click on any of the buttons below, you’ll be doing me a favour by sharing this article with other people.

Why did over a hundred residents go to a Planning Committee site visit on the Saughall Massie fire station proposal?

Why did over a hundred residents go to a Planning Committee site visit on the Saughall Massie fire station proposal?

                                         

Please accept YouTube cookies to play this video. By accepting you will be accessing content from YouTube, a service provided by an external third party.

YouTube privacy policy

If you accept this notice, your choice will be saved and the page will refresh.

Planning Committee (Wirral Council) site visit (APP/17/00306) Saughall Massie fire station, land adjacent to Saughall Massie Road 18th July 2017

Planning Committee (Wirral Council) site visit Saughall Massie APP/17/00306 18th July 2017
Planning Committee (Wirral Council) site visit Saughall Massie APP/17/00306 18th July 2017

In a grassy field on a summer morning, Wirral Council’s Planning Committee met to visit the site for a proposed fire station in Saughall Massie on Wirral Council owned land just off Saughall Massie Road.

Many local residents and two of the three local councillors (Cllr Bruce Berry and Cllr Steve Williams) were there to observe what happened on the site visit.

There were many with placards opposing the planning application for greenbelt reasons.

Cllr Eddie Boult turned up much earlier for the site visit than the other councillors on the Planning Committee.

Cllr Anita Leech, Chair of the Planning Committee opened the site visit and explained the purpose of the site visit and the procedure that would be followed. She asked a planning officer (Matthew Parry-Davies) to introduce the planning application. Unfortunately Matthew’s voice wasn’t very loud.

Matthew Parry-Davies (who works in Wirral Council’s planning department) explained that the revised planning application was for “a single storey two bay community fire station”.

He explained that access to the fire station (if planning permission was granted) would be from Saughall Massie Road. Mr Parry-Davies described the distances to the nearest properties on two different sides of the site.

The footprint of the proposed building and site perimeter had already been pegged out (both the footprint and the building had been reduced compared to the original planning application). The orientation had also been changed. The generator and sprinkler had been relocated and the training tower had been moved too.

Cllr Anita Leech (Chair of the Planning Committee) asked if any of the Planning Committee had any questions.

Cllr Eddie Boult asked for the differences in distance to adjoining properties between the original planning application and revised planning application. Matthew Parry-Davies answered.

Cllr Steve Foulkes asked if there would still be access to the rest of the site for the general public.

Cllr Treena Johnson asked questions about the retractable tower and its height when down and up. Matthew Parry-Davies answered her questions.

Cllr Anita Leech asked how long it would take to put up and down.

Cllr David Elderton answered with how often it would be up.

Cllr Anita Leech (Chair of the Planning Committee) asked if any ward councillors for the area had any questions.

Cllr Steve Williams (a councillor for Moreton West and Saughall Massie ward) pointed out the distance between the perimeter and nearby houses.

Cllr Anita Leech (Chair of the Planning Committee) asked Colin Schofield of Merseyside Fire and Rescue Service to confirm which tape and posts marked the site boundary. He did.

Cllr Anita Leech (Chair of the Planning Committee) confirmed that the blue posts were the site boundary and the red posts were for the building.

Cllr Bruce Berry (a councillor for Moreton West and Saughall Massie ward) asked a question about car parking and asked how vehicles would go on and off the site.

Matthew Parry-Daives answered him.

The Chair of the Planning Committee asked if any ward councillors had any more questions to ask?

Cllr Steve Williams (a councillor for Moreton West and Saughall Massie ward) asked if there would be any controlled burning on the site.

The Chair of the Planning Committee referred to a planning condition in relation to this.

She then asked if anyone else wanted to point out anything “of significance”?

Various residents asked questions or made points about flooding, traffic issues, the site of the generator, vehicles leaving and entering the site, site levels, where fire engines were called out to, traffic, residential amenity and where the optimal position for a fire station to replace West Kirby and Upton was.

Cllrs Eddie Boult and Cllr Steve Foulkes (both on the Planning Committee) made further points.

The site visit ended with the Chair, Cllr Anita Leech thanking everyone for their attendance.

Pictures below this article are photos of the green belt site and people present for the site visit.

Wirral Council’s Planning Committee will meet to decide on planning application (APP/17/00306) for a fire station on land (owned by Wirral Council) adjacent to Saughall Massie Road in Saughall Massie at a public meeting starting at 6.00 pm on the 20th July 2017 in the Civic Hall, first floor, Wallasey Town Hall, Brighton Street, Seacombe, CH44 8ED.

Cllr Eddie Boult (foreground) at the site visit of Wirral Council’s Planning Committee to Saughall Massie 18th July 2017
Cllr Eddie Boult (foreground) at the site visit of Wirral Council’s Planning Committee to Saughall Massie 18th July 2017

Continue reading “Why did over a hundred residents go to a Planning Committee site visit on the Saughall Massie fire station proposal?”

Why did hundreds of residents go to a Planning Committee site visit on the Saughall Massie fire station proposal?

Why did hundreds of residents go to a Planning Committee site visit on the Saughall Massie fire station proposal?

Why did hundreds of residents go to a Planning Committee site visit on the Saughall Massie fire station proposal?

                                         

Please accept YouTube cookies to play this video. By accepting you will be accessing content from YouTube, a service provided by an external third party.

YouTube privacy policy

If you accept this notice, your choice will be saved and the page will refresh.

Planning Committee (Wirral Council) site visit (APP/16/00985) Saughall Massie fire station, land adjacent to Saughall Massie Road

Planning Committee site visit to land off Saughall Massie Road 13th December 2016 Left Cllr Steve Foulkes Right Cllr Anita Leech Chair-min
Planning Committee site visit to land off Saughall Massie Road 13th December 2016 Left Cllr Steve Foulkes (Planning Committee) Right Cllr Anita Leech (Chair, Planning Committee)

In a muddy field on a cold winter morning, Wirral Council’s Planning Committee met to visit the site for a proposed fire station in Saughall Massie on Wirral Council owned land just off Saughall Massie Road.

Many local residents and the three local councillors (Cllr Chris Blakeley, Cllr Bruce Berry and Cllr Steve Williams) were there to observe what happened on the site visit.

The only person there with a placard in favour of the planning application was vastly outnumbered by those with placards opposing the planning application for greenbelt reasons.

Cllr Anita Leech, Chair of the Planning Committee opened the site visit by apologising for being late and explained the purpose of the site visit and the procedure that would be followed. She asked a planning officer to introduce the planning application.

Matthew Parry-Davies (who works in Wirral Council’s planning department) explained that the planning application was for “a single storey two bay community fire station”.

He explained that access to the fire station (if planning permission was granted) would be from Saughall Massie Road. Mr Parry-Davies described the distances to the nearest properties on two different sides of the site.

The outline of the proposed building had been pegged out. A question was asked of Mr Parry-Davies as to where vehicles would exit and enter the proposed fire station.

Cllr Anita Leech (Chair of the Planning Committee) asked if any ward councillors for the area had any questions.

Cllr Chris Blakeley (a councillor for Moreton West and Saughall Massie ward) pointed out that the pegs that were laid out were for the building only, not the curtilage of the site.

Therefore the area of the pegs didn’t include the training area or car park and that if the pegs had been put round whole of the proposed development it would appear much bigger.

There was applause for Cllr Chris Blakeley from many of the residents.

Once the applause had died down, he pointed out that the nearby properties were sheltered accommodation. He referred to a survey of the people in the sheltered accommodation which had shown 85% opposed to the planning application.

Cllr Blakeley received more applause.

The Chair of the Planning Committee asked if any councillors on the Planning Committee wanted to ask questions.

A question was asked by Cllr Kathy Hodson and an answer was given by Matthew Parry-Davies.

After another point was made, Matthew Parry-Davies pointed out that the pegs marked out the footprint of the building. He added that there were different pegs that showed the outline of the site proposed.

The Chair then asked Members of the Planning Committee to look at the boundaries of the site that were in the planning application.

Moving away, the Planning Committee discussed the proposed development around the building, such as the car park. There was a lot of pointing at this point. Distances and elevations were referred to by Mr Parry-Davies.

After more discussion and pointing the Planning Committee returned to its original spot.

The site visit ended with the Chair, Cllr Anita Leech thanking everyone for their attendance and that she may see some of them on Thursday evening.

Pictures below this article are of the green belt site, banners and people present for the site visit.

Wirral Council’s Planning Committee will meet to decide on planning application (APP/16/00985) for a fire station on land (owned by Wirral Council) adjacent to Saughall Massie Road in Saughall Massie at a public meeting starting at 6.00 pm on the 15th December 2016 in the Civic Hall, first floor, Wallasey Town Hall, Brighton Street, Seacombe, CH44 8ED.

photo 1 Land off Saughall Massie Road Saughall Massie 13th December 2016
photo 1 Land off Saughall Massie Road Saughall Massie 13th December 2016

Continue reading “Why did hundreds of residents go to a Planning Committee site visit on the Saughall Massie fire station proposal?”

Would you like to see 2 invoices (totalling £153,250.61) for pre construction work on the Saughall Massie fire station project?

Would you like to see 2 invoices (totalling £153,250.61) for pre construction work on the Saughall Massie fire station project?

Would you like to see 2 invoices (totalling £153,250.61) for pre construction work on the Saughall Massie fire station project?

                                   

Below this are 2 two page invoices to Merseyside Fire and Rescue Service for work by their contractor Wates Construction Ltd. This is for pre-construction work on the Saughall Massie fire station (as far as I know a planning application hasn’t been yet submitted).

One invoice is for £99,686.90 (£119,623.31 including VAT) paid on the 4th March 2016, the second is for £28,022.75 (£33,627.30 including VAT) paid on the 17th March 2016.

There are also some emails that accompany the invoices which show:

a) The contractor originally didn’t put Saughall Massie on the invoice but Prescot (Prescot is about 18 miles away from Saughall Massie and is another fire station project),

b) Merseyside Fire and Rescue Service refused to pay the invoice until it was amended and Saughall Massie put on it,

c) the contractor submitted an amended invoice but then spelt Saughall Massie as Saughall Massey.

Sadly the valuation breakdowns of what these invoices were for which was included in the Draft Payment Notice e-mail has not been shared with me. Apologies if the images below take a while to load, I scanned them in in colour by mistake instead of black and white. This has the effect of increasing the file size.

0 Wates Construction Ltd invoice 26th February 2016 Saughall Massie Fire Station £119623.31 Page 1 of 2
0 Wates Construction Ltd invoice 26th February 2016 Saughall Massie Fire Station £119623.31 Page 1 of 2
1 Wates Construction Ltd invoice 26th February 2016 Saughall Massie Fire Station £119623.31 Page 2 of 2
1 Wates Construction Ltd invoice 26th February 2016 Saughall Massie Fire Station £119623.31 Page 2 of 2
2 email from Neil Bushell to Tina Woods and Stewart Woods re Wates invoice 94903 £99686.09
2 email from Neil Bushell to Tina Woods and Stewart Woods re Wates invoice 94903 £99686.09
3 emails re Saughall Massie Payment Notice Number 1
3 emails re Saughall Massie Payment Notice Number 1
4 emails re Saughall Massie Invoice
4 emails re Saughall Massie Invoice
5 Wates Construction Ltd invoice 26th February 2016 Saughall Massie Fire Station £33627.30 Page 1 of 2
5 Wates Construction Ltd invoice 26th February 2016 Saughall Massie Fire Station £33627.30 Page 1 of 2
6 Wates Construction Ltd invoice 26th February 2016 Saughall Massie Fire Station £33627.30 Page 2 of 2
6 Wates Construction Ltd invoice 26th February 2016 Saughall Massie Fire Station £33627.30 Page 2 of 2
7 email re Prescot Payment Notice Nr 12 - Saughall Massie Payment Notice Nr 2