6 more pages of the Wirral Schools Services Limited contract with Wirral Council

6 more pages of the Wirral Schools Services Limited contract with Wirral Council

6 more pages of the Wirral Schools Services Limited contract with Wirral Council

                    

Continues from The first 17 pages of Wirral Council’s contract with Wirral Schools Services Limited. This is a further six pages in the same contract.

THIS AGREEMENT is made on 27 March 2001.

BETWEEN:

(1) WIRRAL BOROUGH COUNCIL of Town Hall, Brighton Street, Wallasey, Wirral, Merseyside, CH44 8ED (the “Authority”; and

(2) WIRRAL SCHOOLS SERVICES LIMITED a company incorporated under the laws of England and Wales with registered number 41156367 whose registered office is at Frogmore Park, Watton-at-Stone, Hertford SG14 3RU (“Project Co”).

BACKGROUND:

(A) By virtue of sections 13 and 14 of the Education Act 1996, the Authority as local education authority is under statutory duties to secure that efficient primary and secondary education are available to meet the needs of the population of its area and that sufficient schools for providing such education are available for its area.

(B) By virtue of section 16 of the Education Act 1996, the Authority as local education authority may, for the purposes of fulfilling the above duties, establish and maintain primary and secondary schools.

(C) By a notice dated 17 November 1998 in the Official Journal, the Authority invited expressions of interest from appropriately qualified tenderers for the provision of accommodation and related support services for eight secondary schools and one primary school in accordance with the Government’s Private Finance Initiative.

(D) Project Co has submitted a proposal which, as negotiated through the negotiated tender process, has been agreed to by the Authority.

(E) The Authority and Project Co have agreed to work together in a spirit of co-operation to achieve the objectives of the Project. The Authority and Project Co have agreed to carry out the Project on the terms and conditions set out in this Agreement.

(F) The Project is a private finance initiative project within the meaning of the Housing Grants, Construction and Regeneration Act 1996.

IT IS AGREED as follow:

RMLIB01 #659790 v14 03/04/2001 15:25

PART 1 – INTERPRETATION

1. DEFINITIONS AND INTERPRETATION

1.1 Definitions

In this Agreement (including the Background), the following terms shall, unless the contract otherwise requires, have the following meanings:

“1999 Act” means the Local Government Act 1999;

“Academic Year” means from the first day to the last day (excluding holidays) of the school year, such period not to be more than 195 days;

“Accommodation Actual Completion Date” means, in respect of the Accommodation Works at a Site, the date on which those Accommodation Works are Complete, being either the date stated in the certificate issued persuant to Clause 14.6 (Completion) or if this date is disputed in accordance with the Fast Track Resolution Procedure, the date determined under that procedure, as being the date upon which such certificate should have been issued;

“Accommodation Completion Date” means, in relation to the Accommodation Works at a Site, the date set out in column (1) of the Schedule of Key Dates by which such Accommodation Works must be Complete;

“Accommodation Services” means the services described in the Accommodation Services Output Specifications;

“Accommodation Services Output Specifications” means the specifications contained in Schedule 5 (Accommodation Services) as may be amended by a Variation or otherwise in accordance with this Agreement;

“Accommodation Works” means the works listed in Schedule 3 Part 4A;

“Acquired Rights Directive” means Council Directive 77/187 EEC as amended;

“Act of Vandalism” means a wilful, deliberate or malicious act carried out by Authority staff or pupils, guests, visitors or other persons authorised by the Authority who are properly on the relevant Site which results in damage to the relevant Facility or Site or any Fixed and/or Moveable Equipment thereon;

“Actual Date of Completion” means:

RMLIB01 #659790 v14 03/04/2001 15:25

(a) in respect of the Initial Works at a Site, the date on which those Initial Works are Complete, being either the date stated in the certificate issued persuant to Clause 14.4 (Completion) or if this date is disputed in accordance with the Fast Track Resolution Procedure, the date determined under that procedure, as being the date upon which such certificates should have been issued; or

(b) in respect of any Variation Works, the date on which the Variation Works are Completed in accordance with the relevant Variation Report agreed or determined (as appropriate) pursuant to Clause 32 (Variations) and certified as such pursuant to Clause 14.4 (Completion);

“Adjudication” means the procedure set out in paragraph 3 of Schedule 12 (Dispute Resolution);

“Adjudicator” means an adjudicator appointed under paragraph 3 of Schedule 12 (Dispute Resolution);

“Affected Party” means a Party affected by the occurence of the events listed in paragraphs (a), (b) and (c) of the definition of Force Majeure;

“Agenda 21” means the action plan establishing a framework for law in the field of sustainable development known as “Agenda 21” adopted at the United Nations Conference on Environment and Development held in Rio de Janeiro in June 1992;

“Agent” means Societété Générale of SG House, 41 Tower Hill, London, EC3N 4SG and its successors and assigns;

“Alternative Scheme” means one or more pensions scheme(s) each of which is approved or capable of approval under Chapter 1 Part XIV of the Income and Corporation Taxes Act 1988 or the trustees of such a scheme as the case may be;

“Amended Plans” has the meaning given in Clause 32.12 (Plans);

“Ancillary Documents” means:

(a) the Shareholder’s Agreement;

(b) Project Co’s memorandum of association and articles of association;

(c) the D&B Contract;

(d) the Support Services Management Agreement;

RMLIB01 #659790 v14 03/04/2001 15:25

3

(e) the Direct Agreements;

(f) the D&B Contract Performance Guarantee; and

(g) the Support Services Management Agreement Performance Guarantee;

“Annual Debt Service Cover Ratio” or “ADSCR” whilst the Initial Funding Agreements are in force shall have the meaning given to Senior Debt Service Cover Ratio in the Initial Funding Agreements and thereafter means in respect of any period for which it falls to be calculated the ratio of A:B where:

A is the aggregate of Cash Available for Debt Service for that period; and

B is the Annual Debt Service Obligations for that period;

“Annual Maintenance Programme” means the Maintenance programme agreed or determined pursuant to Clause 19.3 (Annual Maintenance Programme);

“Annual Net Third Party Profit” means Gross Third Party Revenues earned in respect of third party use during a Year less the Third Part Costs incurred in respect of third party use during that Year;

“Annual Utility Services Consumption Targets” has the meaning given in paragraph 2.1 of Part 6 (Utility Services) of Schedule 4 (Payments);

“Appeal” means all or any of the following:

(a) an appeal to the Secretary of State in accordance with Section 78 of the Planning Acts against:

(i) a conditions attached to the Full Planning Permissions or Variation Planning Approvals and/or a refusal of a planning application for Planning Approvals and/or Variation Planning Approvals; or

(ii) non-determination of a planning application for Planning Approvals and/or Variation Planning Approvals; or

(b) the reference of a planning application to the Secretary of State under Section 77 of the Planning Acts,

and the expression “to Appeal” shall be construed accordingly;

RMLIB01 #659790 v14 03/04/2001 15:25

4

“Approved Leased Equipment” means sanitary equipment, fire detection and prevention systems, telephone systems, photocopiers and vehicles;

“Arbitration” means the procedure set out in paragraph 4 of Schedule 12 (Dispute Resolution);

“Arbitrater” means an arbitrator appointed in accordance with paragraph 4 of Schedule 12 (Dispute Resolution);

“Asbestos” means any of the following minerals; crocidolite, amosite, chrysolite, fibrous actinolite, fibrous antthophyllite, fibrous tremolite and any mixture containing any of those minerals;

“Asset Register” means, with respect to each Facility, the asset register to be compiled by Project Co pursuant to Clause 22.18 (Asset Registers);

“Associated Company” means, in respect of a relevant company, a company which is a Subsidiary or a Holding Company of that relevant company or a company which is a Subsidiary of a Holding Company of that relevant company but not that relevant company itself and, in the case of Project Co, shall include each of the Consortium Members (the terms “Holding Company” and “Subsidiary” bearing the meanings defined in part XXXVI of the Companies Act 1985);

“Authority’s Confidential Information” has the meaning given in Clause 48.1 (The Authority’s Confidential Information);

“Authority’s D&B Contract Direct Agreement” means the direct agreement of the same date as this Agreement between the Authority, the D&B Contractor and Project Co;

“Authority’s Service Adviser” means the person appointed by the Authority (and notified to Project Co) to act pursuant to Clause 40 (Representatives);

“Authority’s Share” means the percentage figures in the fourth column of the table set out below corresponding to the amount of Cumulative Capital Expenditure at the relevant time, as shown in the first column of the table set out below:

Cumulative Capital Expenditure Project Co’s Share Cumulative Cost to Project Co Authority’s Share
£0 – £0.6 million 100% £600,000 0%
£0.6 – 1.2 million 75% £1,050,000 25%

RMLIB01 #659790 v14 03/04/2001 15:25

5

£1.2 – 1.8 million 50% £1,350,000 50%
£0.6 – 2.4 million 25% £1,500,000 75%
Over £2.4 million 0% £1,500,000 100%

“Authority’s Solicitors” means Rowe & Maw of 20 Black Friars Lane, London EC4V 6HD;

“Authority’s Support Services Management Direct Agreement” means the direct agreement of the same date as this Agreement between the Authority, the Support Services Manager and Project Co;

“Authority’s Works Adviser” means the person appointed by the Authority (and notified to Project Co) to act pursuant to Clause 40 (Representatives);

“Availability Deduction” has the meaning given in Part 1 (Definitions) of Schedule 4 (Payments);

“Base Case Financial Model” means the financial model as at the Effective Date setting out the basis on which the financing of the Project and the costs of and revenue from the Project have been calculated by Project Co (including the assumptions used, the cell logic network for the financial model software and any software and accompanying documentation necessary to operate the financial model) in the Agreed Form;

“Bebington” means Bebington High School;

“Bebington Asset Register” means the asset register to be compiled by Project Co pursuant to Clause 22.18 (Asset Registers);

“Bebington Headlease” means the lease between the Authority and Project Co substantially in the form set out in Part 1 (Bebington Headlease) of Schedule 1 (Land);

“Bebington Site” means the land identified in the Bebington Headlease and shown edged red on Plan B;

“Benchmarked Price” has the meaning given in paragraph 2.4 of Part 8 (Value for Money Testing) of Schedule 4 (Payments);

“Benchmarking” means subjecting a Support Service to the market price comparison procedure set out in Part 8 (Value for Money Testing) of Schedule 4 (Payments) with the aim of ensuring that the Support Service being tested is provided

RMLIB01 #659790 v14 03/04/2001 15:25

6

Continues at 38 more pages of the Wirral Schools Services Limited private finance initiative (PFI) contract with Wirral Council.

If you click on any of these buttons below, you’ll be doing me a favour by sharing this article with other people. Thanks:

The first 17 pages of Wirral Council's contract with Wirral Schools Services Limited

The first 17 pages of Wirral Council’s contract with Wirral Schools Services Limited

The first 17 pages of Wirral Council’s contract with Wirral Schools Services Limited

                           

Edited 13/11/2014 to correct “Wirral School Services Limited” to “Wirral Schools Services Limited”.

Below is the first 17 A4 pages of Wirral Council’s contract with Wirral Schools Services Limited. I requested it as part of the 2013/14 audit. Sadly it’s so long I’ll probably just have to scan the rest of it in or OCR it.

There are a further 114 pages in this section.

Private & Confidential

Dated 9th September 2004

WIRRAL BOROUGH COUNCIL (1)
WIRRAL SCHOOLS SERVICES LIMITED (2)

===================================================================================================================
DEED OF AMENDMENT AND RESTATEMENT relating to Wirral Schools PFI Project
===================================================================================================================

ADDLESHAW GODDARD

Contents
Clause Page

1 Interpretation ......................................... 1
2 Effective Date ......................................... 1
3 Amendment and restatement .............................. 2
4 Confirmation ........................................... 2
5 Variations, amendments and payments .................... 2
6 Release by the Authority ............................... 4
7 Release by Project Co .................................. 4
8 Governing law and dispute resolution ................... 4

Schedule

1. Conditions ............................................ 5
   Part 1 - Conditions to be satisfied by Project Co ..... 5
   Part 2 - Conditions to be satisfied by the Authority .. 6
2 Amendments to the Project Agreement .................... 7
3 Details of Variations referred to in clause 5.1 ........ 8
4 Schedule of Payments referred to in clause 5.2(b) ...... 9
5 Outstanding items ..................................... 10

2-1000834-13

This Deed of Amendment and Restatement is made on the 9th day of September 2004

Between

(1) Wirral Borough Council of Town Hall, Brighton Street, Wallasey, Wirral, Merseyside CH44 8ED (Authority); and (signature)

(2) Wirral Schools Services Limited, a company incorporated under the laws of England and Wales with registered number 4115637 whose registered office is at Frogmore Park, Walton-at-Stowe, Hertford SG14 3RU (Project Co).

Whereas

(A) The Authority has appointed Project Co under an agreement dated 27 March 2001 (Project Agreement) to finance, design and construct and to provide certain services in respect of certain schools in Wirral.

(B) The Authority and Project Co have agreed to vary the Project Agreement in the manner hereinafter appearing and to agree certain variations to the Project as hereinafter described.

It is agreed

1 Interpretation

1.1 In this Deed, but save as provided for by clause 1.2, the following expressions shall bear the following meanings:

D&B Deed of Amendment and Restatement means a deed of that name (or about) the same date as this Deed between Project Co and the D&B Contractor amending and restating the D&B Contract

Effective Date means the date upon which the parties confirm to each other in writing pursuant to clause 2.1 that the conditions set out in schedule 1 have been satisfied or waived

Revised Base Case Financial Model means the revision of the Base Case Financial Model as at the Effective Date in the Agreed Form

Subcontract Deeds of Amendment and Restatement means:

(a) the D&B Deed of Amendment and Restatement; and
(b) the Support Services Deed of Amendment and Restatement

Support Services Deed of Amendment and Restatement means a deed of that name of (or about) the same date as this Deed between Project Co and the Support Services Manager amending and restating the Support Services Management Agreement

1.2 Unless stated to the contrary in this Deed, words and phrases used in this Deed with initial capital letters but not defined herein shall have the meanings ascribed to them in the Project Agreement.

1.3 Unless stated to the contrary, references in this Deed to any clause or schedule or appendix are references to such clause or schedule or appendix of or to this Deed.

1.4 Words importing the single number only include the plural number and vice versa.

2 Effective Date

2.1 The provisions of clauses 3, 5 (save for the acknowledgements set out in clauses 5.2(b) and 5.2(d)), 6 and 7 shall have no effect unless and until:

1

2-1000834-13

(a) the Authority shall have confirmed in writing to Project Co that all of the conditions set out in part 1 of schedule 1 shall have been satisfied or waived; and

(b) Project Co shall have confirmed in writing to the Authority that all of the conditions set out in part 2 of schedule 1 shall have been satisfied or waived.

2.2 Each of the Authority and Project Co shall use their respective best endeavours to procure that the conditions set out in clause 2.1 are satisfied as soon as reasonably practicable following the date of this Deed, provided always that, if the Effective Date has not occurred on or before 31 August 24 September 2004, either party shall be entitled to terminate this Deed at any time thereafter upon giving written notice to the other party. (signature)

2.3 Without prejudice to any antecedent breaches of this Deed, if either party terminates this Deed pursuant to clause 2.2 then the Authority shall be entitled to recover in full from Project Co within 5 Working Days of the date of receipt of any notice served pursuant to clause 2.2 the amounts paid by the Authority to Project Co in connection with this Deed prior to the date of termination as set out in clause 5.2 and neither party shall be entitled to bring any claim against the other party as a result of such termination.

2.4 The Authority shall, within 10 Working Days after the Effective Date, deliver to Project Co a duly executed certificate issued pursuant to the Local Government (Contracts) Act 1997 in relation to this Deed.

2.5 Project Co shall procure the delivery by Liberty Mutual Insurance Company (UK) Limited, within 10 Working Days after the Effective Date, of written confirmation of its consent to the D&B Deed of Amendment and Restatement and that the D&B Performance Bond and Retention Bond (in each case, as defined in the D&B Contract) remain effective.

3 Amendment and restatement

With effect from the Effective Date the Project Agreement shall be amended and restated so as to give effect to the amendments set out in schedule 2. The parties agree that the amendments to the Project Agreement and Schedules set out in schedule 2 constitute the only pages of the Project Agreement and Schedules where changes to the text have been agreed between the parties.

4 Confirmation

The parties confirm that the Project Agreement remains in full force and effect save as amended by this Deed.

5 Variations, amendments and payments

5.1 The parties agree that:

(a) as a result of the matters contained in or referred to in this Deed, namely the carrying out of works by Project Co (whether before or after the Effective Date):

(i) required to be undertaken for the removal of Asbestos at the Facilities within the period prior to the last Actual Date of Completion to occur; and

(ii) as a result of Variations instructed and/or requested in writing by the Authority pursuant to Clause 32 of the Project Agreement up to and including 7 June 2004,

the Design and Build Periods in respect of the Sites have been extended as set out in Part 3 of Schedule 3 to the Project Agreement (as amended and restated in accordance with this Deed); and

(b) without prejudice to the Authority’s entitlement to request Variations pursuant to the Project Agreement, Project Co shall carry out such variations to the Works as are nominated by the Authority in its discretion up to (but not exceeding) the value of

2

2-1000834-13

£115,000 (unindexed) which variations Project Co shall carry out and complete at no cost to the Authority; and

(c) Project Co shall shall carry out and complete the Variations set out in schedule 3 to this Deed by the respective dates set out against each such Variation in schedule 3 (and, to avoid doubt, such Variations shall be carried out and completed at no additional cost to the Authority),

provided always that:

(i) the Authority shall be fully responsible for any planning or judicial review risk associated with the carrying out of any Variation referred to in this clause 5.1(c); and

(ii) the Authority shall be entitled to deduct liquidated and ascertained damages (LADs) from the Services Contract Payment at a rate of £55 per Variation for each day in excess of the relevant Completion Date for which any Variation as referred to in this clause 5.1(c) is not complete.

5.2

(a) The parties acknowledge and agree that there is a difference between the Services Contract Payment set out in Part 4 of Schedule 5 to the Project Agreement and the Services Contract Payment set out in the Base Case Financial Model. In order to rectify this difference and by way of full and final settlement of the costs and expenses incurred or to be incurred by Project Co as a result of the implementation of variation works including the change in building design at Leasowe Primary and the implementation (whether before or after the Effective Date) of works to deal with Asbestos discovered in the Facilities within the period prior to the last Actual Date of Completion to occur (in accordance with Clause 16.4 of and Schedule 15 to the Project Agreement), the Authority has agreed to:

(i) change the Expiry Date to 31 July 2031 in order to enable Project Co to raise additional finance (provided always that the amount of principal taken into account in calculating Senior Debt (as shown in the Revised Base Case Financial Model) shall not increase by more than £3,000,000.00, compared with the amount of principal shown for the same date in the Base Case Financial Model, by reason of the raising of such additional finance); and

(ii) pay to Project Co the sum of £3,340,000.00, such sum to be paid in accordance with the remainder of this clause 5.2.

(b) The parties acknowledge that, of the sum referred to in clause 5.2(a)(ii), the sum of £1,800,000.00 has been paid by the Authority to Project Co (and Project Co acknowledges that it has received such amount from the Authority). The remaining sum of £1,540,000.00 shall be due and payable by the Authority to Project Co in the sums and on the dates set out in schedule 4.

(c) Project Co shall submit a valid VAT invoice to the Authority in respect of each of the amounts referred to in clause 5.2(b).

(d) Project Co acknowledges that it has received a payment of £1,186,618.10 (inclusive of VAT) from the Authority in relation to certain costs incurred by Project Co in removing Asbestos. The parties agree that a further sum of £35,000 (which represents the VAT element outstanding on a £200,000 payment on account made by the Authority) remains to be paid by the Authority to Project Co and that the Authority shall pay such amount to Project Co within 30 days of receipt of a valid VAT invoice in respect of the same.

(e) The parties agree to procure that Schedule 4 to the Project Agreement shall, not later than the last Actual Date of Completion to occur, be revised to reflect any changes to the drawings or accommodation schedules as may be necessary, whether arising

3

2-1000384-13

pursuant to this Deed or otherwise, but provided always that any such revision shall not result in any increase to the Services Contract Payment as set out in the Base Case Financial Model.

(f) and (g) – please see continuation sheet overleaf (signature)

Outstanding items

5.3 In consideration of receipt of the amounts referred to in clause 5.2, Project Co shall carry out and complete the works set out in schedule 5 (“Outstanding Items“) and, to avoid doubt, Project Co shall not be entitled to any additional payment in respect of such works.

6 Release by the Authority

6.1 On and with effect from the Effective Date:

(a) the Authority irrevocably waives and releases to Project Co any claim or Losses it may have or which may have arisen consequent upon any breach or alleged breach of any obligation of Project Co contained in the Project Agreement arising prior to the Effective Date in connection with the matters referred to in clause 5.1(a) including without limitation in relation to the issue of any Non-Completion Certificate; and

(b) the Authority irrevocably and unconditionally provides its consent, insofar as such consent may be necessary or required to be given under the Project Agreement, to any matters contained in or referred to in this Deed.

7 Release by Project Co

7.1 On and with effect from the Effective Date Project Co irrevocably waives and releases to the Authority any claim or Losses it may have or which may have arisen consequent upon any breach or alleged breach of any obligation of the Authority contained in the Project Agreement arising prior to the Effective Date in connection with the matters referred to in clause 5.1(a) including without limitation to the issue of any Non-Completion Certificate. Without prejudice to the foregoing, Project Co acknowledges that:

(a) the amendment to the Expiry Date referred to in clause 5.2(a)(i);

(b) the payment of the financial amounts shown in clause 5.2; and

(c) the amendments made to the Schedule of Key Dates referred to in clause 5.1(a),

shall constitute Project Co’s sole compensation in respect of the matters contained within this Deed, including without limitation any claim against the Authority under Clause 16.4 of the Project Agreement or otherwise for costs, expenses, losses, prolongation or disruption expenses or loss of profit arising from any works (whether such works are carried out before or after the Effective Date) required to deal with Asbestos discovered at the Facilities within the period prior to the last Actual Date of Completion to occur.

8 Governing law and dispute resolution

8.1 The law of this Deed is English law.

8.2 Any dispute arising out of or in connection with this Deed shall be resolved in accordance with the procedure set out in Clause 49 (Dispute Resolution Procedure) of the Project Agreement. Subject as aforesaid, the parties agree that the courts of England and Wales shall have exclusive jurisdiction to hear and settle any action, suit, proceeding or dispute in connection with this Deed and irrevocably submit to the jurisdiction of those courts.

In Witness the parties have caused this Deed to be duly executed on the date set out above.

4

2-10000834-13

(f) The parties acknowledge that the extension to the Contract Term hereby agreed (the “Contract Extension“) will enable Project co to raise additional funding to facilitate Project Co’s performance of its obligations under the Project Agreement and this Deed, and the Authority agrees that on the occasion of the first financing of the Contract Extension (whether or not the Contract Extension is financed for the first time as part of a Refinancing (as that term is defined in clause 4.1 of the Project Agreement) or otherwise) all sums thereby raised up to (but not exceeding) the sum of three million pounds (£3,000,000.00) and arising solely out of the Contract Extension shall accrue solely to Project Co provided that (for the avoidance of doubt) that parties hereto agree that on any Refinancing (as that term is defined in clause 4.1 of the Project Agreement) taking place after the first financing of the Contract Extension as aforesaid the provisions of clause 4.1 of and Schedule 2 Part 8 (Rules for Refinancing) to the Project Agreement shall apply in full to the Contract Term as hereby extended.

(g) For the purposes of clause 4.1 of the Project Agreement, the Authority hereby grants its consent to the first financing of the Contract Extension (but not further or otherwise). (signature)

2-1076380-1

Schedule 1
Conditions
Part 1 – Conditions to be satisfied by Project Co

Delivery by Project Co to the Authority of the documents listed below in form and substance satisfactory to the Authority. Where listed as a duly certified copy, the document must be certified by a director or the secretary of Project Co as being a true copy:

1. A copy, duly certified, of minutes of a meeting of the board of directors of Project Co evidencing:

(a) consideration by the directors of:

(i) a final draft of this Deed and the Subcontract Deeds of Amendment and Restatement;

(ii) Project Co’s rights and obligations under this Deed and the Subcontract Deeds of Amendment and Restatement; and

(iii) any limit or restriction on any of Project Co’s powers or any limit or restriction on the rights or ability of the directors to exercise any of Project Co’s powers; and

(b) a resolution of the board of directors approving the execution, delivery and performance by Project Co of this Deed and the Subcontract Deeds of Amendment and Restatement and authorising a specific person or persons to execute and deliver this Deed and the Subcontract Deeds of Amendment and Restatement and sign and despatch all notices and other communications required or permitted to be given by Project Co under this Deed and the Subcontract Deeds of Amendment and Restatement.

2. A specimen of the signature of each person authorised by Project Co to execute this Deed and the Subcontract Deeds of Amendment and Restatement and to sign and despatch all notices and other communications required or permitted to be given by Project Co thereunder.

3. A copy, duly certified, of each of this Deed and the Subcontract Deeds of Amendment and Restatement.

4. The Revised Base Case Financial Model.

5

2-10000834-13

Part 2 – Conditions to be satisfied by the Authority

Delivery by the Authority to Project Co of the documents listed below all in form and substance satisfactory to Project Co:

1. Copies of such (if any) of the Direct Agreements as may be required by the Lenders to be executed by the Authority, executed by the Authority (but not, for the avoidance of doubt, the other parties to the Direct Agreements); and

2. Certified copies of the appropriate minute of the Authority which evidences the delegated authority of the officer signing this Deed.

6

2-10000834-13

Schedule 2
Amendments to the Project Agreement

7

2-10000834-13

CONFORMED COPY

DATED       27 March 2001

(1) WIRRAL BOROUGH COUNCIL

(2) WIRRAL SCHO OLSSCHOOLS SERVICES LIMITED

(signature)

===================================================================================================================

PROJECT AGREEMENT

Amended and Restated pursuant to a Deed of Amendment and Restatement dated 9th September 2004

===================================================================================================================

ROWE & MAW
20 Black Friars Lane
London EC4V 6HD

Tel: 020 7248 4282
Fax: 020 7248 2009

Ref: 617/343/476/27909.1

CONTENTS

CLAUSE SUBJECT MATTER PAGE

1. Definitions and Interpretation 2
2. Conditions Precedent 4344
3. Ancillary Documents 4647
4. Funding Arrangements, Direct Agreements, Guarantees and Prohibition on Diversification 4748
5. Term 5051
6. Planning 5051
7. Works 5657
8. Project Programme and Extensions of Time 5961
9. Design Development 6264
10. Standards of Design and Workmanship 6364
11. D & B Contract 6365
12. Decant Programme 6465
13. Care of the Sites and Reinstatement 6466
14. Inspection and Completion 6567
15. CDM Regulations 6870
16. Defects 6971
17. Fossils and Antiquities 7072
18. Services and Phase-in 7274
19. Maintenance 7678
20. Utility Services and Catering 8284
21. Value for Money Testing and Best Value 8587
22. Equipment and Materials 8789
23. Payments to Project Co 9395
24. Performance Regime 98100
25. Provisions Relating to Land 101103
26. Authority Access 103105
27. Site Licences and Leases 104106
28. Obligations of Project Co in Respect of the Sites and the Authority’s Obligations in Respect of Land 107109
29. Rates, Taxes and Outgoings 109111
30. Quality Assurance 110112
31. Reports and Records 112114
32. Variations 117119
33. Change in Law 130132
34. Indemnity and Liability Limitation 132134
35. Environmental Liability 138140
36. Insurance 139141
37. Events of Default and Termination 146148
38. Compensation on Termination 151153
39. Consequential Arrangements on Termination 155157
40. Representatives 159161
41. Sub-Contracting 161163

RMLIB01 #659790 v14 03/04/2001 15:25

i

42. Assignment 162164
43. Change of Control 163165
44. Force Majeure 164166
45. Warranties and Disclaimers 166168
46. Employees 161171
47. Intellectual Property and Data 179181
48. Confidentiality and Publicity 181183
49. Disputes 185187
50. Agency 185187
51. Personal Data 186188
52. Corrupt Gifts and Payments of Compensation 188190
53. Health and Safety, Site Rules and Occupiers Liability 190192
54. Miscellaneous 192194
55. Governing Law and Jurisdiction 196198

RMLIB01 #659790 v14 03/04/2001 15:25

ii

INDEX OF SCHEDULES

SCHEDULE HEADING
SCHEDULE 1 LAND
Part 1 Bebington Headlease
Part 2 Hilbre Headlease
Part 3 Park High Headlease
Part 4 Prenton High Headlease
Part 5 South Wirral High Headlease
Part 6 Wallasey Headlease
Part 7 Not used
Part 8 Weatherhead Headlease
Part 9 Wirral Girls Headlease
Part 10 Bebington Underlease
Part 11 Hilbre Underlease
Part 12 Park High Underlease
Part 13 Prenton High Underlease
Part 14 South Wirral High Underlease
Part 15 Wallasey Underlease
Part 16 Not used
Part 17 Weatherhead Underlease
Part 18 Wirral Girls Underlease
Part 19 Plans

SCHEDULE 2 FINANCIAL MATTERS
Part 1 Lenders’ Direct Agreement
Part 2 The Council’s Design and Building Contract Direct Agreement
Part 3 The Council’s Support Services Management Direct Agreement
Part 4 Design and Building Contract Performance Guarantee
Part 5 Support Services Management Agreement Performance Guarantee
Part 6 Initial Senior Funding Agreements
Part 7 Other Initial Funding Agreements
Part 8 Rules for Refinancing

SCHEDULE 3 WORKS

Part 1 Design Development Procedure
Part 2 Prohibited Materials

RMLIB01 #659790 v14 03/04/2001 15:25

iii

Part 3 Schedule of Key Dates
Part 4 Outline Design Documents
Part 5 The Completion Standards
Part 6 Decant Programme Methodology
Appendix 1 Decant Programme: Park High
Appendix 2 Decant: Further Obligations
Part 7 Handback Requirements
Part 8 Project Programme
Part 9 Construction Site Rules
Part 10 Handback Survey
SCHEDULE 4 PAYMENTS
Part 1 Definitions
Part 2 Services Contract Payment
Part 3 Performance Deduction Look-up Table
Part 4 Table of Service Units per School
Part 5 Monitoring
Part 6 Utility Services
Part 7 Third Part Use
Part 7A Catering
Part 8 Value for Money Testing
Appendix 1 Form of Performance and Payment Report
SCHEDULE 5 ACCOMMODATION SERVICES OUTPUT SPECIFICATION
SCHEDULE 6 SUPPORT SERVICES OUTPUT SPECIFICATION
Part 1 Building and Asset Maintenance Output Specification
Part 2 Support Service Requirements and Performance Tables
Part 3 Service Level Agreements
Part 4 Service Level Agreements Alteration Procedure
SCHEDULE 7 REPORTS AND RECORDS
Part 1 Reports
Part 2 Records
SCHEDULE 8 VARIATION
Variation Notice
SCHEDULE 9 INSURANCE
Part 1 The Part I Insurance Period

RMLIB01 #659790 v14 03/04/2001 15:25

iv

Part 2 The Part 2 Insurance Period
Appendix 1 Endorsements
Appendix 2 Broker’s Letter of Undertaking
Appendix 3 Business Interruption Insurance – the Authority’s Obligations as Insurer
Appendix 4 Schedule of Insured Parties
SCHEDULE 10 LIAISON COMMITTEE
SCHEDULE 11 COMPENSATION ON TERMINATION
Part 1 Definitions
Part 2 Project Co Default
Part 3 Authority Default
Part 4 Notice by the Authority
Part 5 Force Majeure, Uninsurability and Planning Challenge
Part 6 Corrupt Gifts
SCHEDULE 12 DISPUTE RESOLUTION
SCHEDULE 13 SENIOR REPRESENTATIVES
SCHEDULE 14 COMPENSATION EVENTS
SCHEDULE 15 METHODOLOGY FOR ASBESTOS
Appendix 1 MB Wirral Policy
Appendix 2 Asbestos Survey Risk Assessment
SCHEDULE 16 LIQUIDATED DAMAGES
SCHEDULE 17 QUALITY SYSTEMS
Part 1 Design and Build Period Quality System
Part 2 Operational Period Quality System
Appendix A Quality Policy
Appendix B Certificate of Approval
Appendix C Proposed QA Implementation Plan
Appendix D Contact Directory
Appendix E Local Procedures
SCHEDULE 18 EMPLOYEES
Part 1 Employee Information
Part 2 Terms and Conditions of Employment
SCHEDULE 19 ADMISSION AGREEMENTS AND BONDS
Part 1 Jarvis Workspace FM Limited
Part 2 Compass Group PLC

RMLIB01 #659790 v14 03/04/2001 15:25

v

Part 3 MTL Commercial Limited
SCHEDULE 20 STAFF SECURITY PROTOCOL
SCHEDULE 21 OPERATIONAL SITE RULES
SCHEDULE 22 DRAFT TRANSITIONAL SERVICES AGREEMENT
SCHEDULE 23 CITY LEARNING CENTRE
SCHEDULE 24 NEW MOVEABLE EQUIPMENT SCHEDULE OF RATES

RMLIB01 #659790 v14 03/04/2001 15:25

vi

Continues at 6 more pages of the Wirral Schools Services Limited contract with Wirral Council.

If you click on any of these buttons below, you’ll be doing me a favour by sharing this article with other people. Thanks:

Trade unions march on Wirral Council, only to hear how wonderful the 2014 Open Golf championship was

Trade unions march on Wirral Council, only to hear how wonderful the 2014 Open Golf championship was

Trade unions march on Wirral Council, only to hear how wonderful the 2014 Open Golf championship was

                                                        

Cllr Phil Davies at the start tells people how pleased he is to see so many members of the public at the Cabinet meeting of the 6th November 2014
Cllr Phil Davies tells people at the start how pleased he is to see so many members of the public at the Cabinet meeting of the 6th November 2014

Please accept YouTube cookies to play this video. By accepting you will be accessing content from YouTube, a service provided by an external third party.

YouTube privacy policy

If you accept this notice, your choice will be saved and the page will refresh.

The first part of the Cabinet meeting can be watched above (apart from a short video that has been edited out.

Prior to last night’s Cabinet meeting there was a trade union march from Seacombe Ferry to Wallasey Town Hall. Wirral Council’s Cabinet have managed to not just cause public sector union troubles, as part of the Cabinet has managed to cause trade union issues in my private sector workplace too.

The trade union strife and march is already covered in the Liverpool Echo.

Wirral Council of course knew this was coming, so with the “Green” party in the audience the first part of the meeting was about the “Royal and Ancient” (no, I’m not referring in any way to Wirral Council’s Cabinet) & the recent Open Golf Tournament.

So are Wirral Council’s Cabinet caught in the political equivalent of madly swinging at the ball in a sand bunker whilst there’s union trouble brewing back at the club house or does Cllr Phil “Golf Club Captain” Davies just take the “rough” with the smooth?

Ed – enough of the golf puns John!

Well caught in the PR nightmare of trade union issues, obviously Wirral Council had to have a “good news” story to tell.

So the meeting started by someone telling the audience about how great TV coverage and coverage about Wirral on websites was. For a moment I thought I was in a bizarre dream. Usually Cllr Phil Davies is saying how “irresponsible” the press is or how they’ve got things wrong. A politician having to sit through a meeting where somebody says nice things about the press is a rare event indeed!

Then it got even better, a guy said there was an “economic impact” of TV and online coverage about Wirral.

Oh boy, I thought. I really am just dreaming now aren’t I? They’ve actually asked somebody to assess the economic importance to Wirral of this blog about Wirral Council and associated Youtube channels (this is the main one and this one is temporarily used whilst the dispute with Sony over Lyndale School coverage of a previous Cabinet meeting is sorted).

Thankfully the guy was only talking about golf more specifically the recent Open Golf Tournament. Hmmmm!

So when I got an email from Surjit Tour telling me to remove coverage about the Open Golf tournament from my blog he was in fact attempting to harm the Wirral economy? Well blow me down with a feather and call me Nora (no offence Leonora).

My reply to him at the time obviously should have been, don’t you realise Mr. Tour the economic harm you’re trying to ravage on the Wirral economy? Obviously a completely missed opportunity on my part and should’ve been followed by don’t you realise tourism jobs on the Wirral depend on media coverage of the Open Golf? And indeed how without that blog post would we have got classic quotes such as local tailor Cllr Walter Smith saying the quotable line “I must say I enjoyed lavish hospitality” on BBC Radio Merseyside?

So next time a Wirral Council councillor stops me filming a public meeting, I will not only remind them of the law states but I will accuse them of the “economic carnage” and people that’ll be put out of work that they’re deliberately inflicting on the local economy. Probably hyperbole, but then a lot of politics often seems to be hyperbole.

If you click on any of these buttons below, you’ll be doing me a favour by sharing this article with other people. Thanks:

Wirral Council taking people to court who can't pay Council Tax: £2,196 Paying for it using a Barclaycard in the name of M Burns: Priceless

Wirral Council taking people to court who can’t pay Council Tax: £2,196 Paying for it using a Barclaycard in the name of M Burns: Priceless

Wirral Council taking people to court who can’t pay Council Tax: £2,196
Paying for it using a Barclaycard in the name of M Burns: Priceless

                                                                        

As I’d better declare this interest at the start, I will state that my wife is the person in this household liable for Council Tax.

Just when the satirists must have thought that the filming ban of public meetings of Wirral Council would led to a deficit of quotable quotes from local councillors, below is a credit card statement from November 2013. Quite what the blacked out bit states or the other ten pages I’m not sure.

Now I’m not saying people shouldn’t pay Council Tax, however thanks to decisions made by Wirral Council’s Cabinet, households that hadn’t paid Council Tax before because they had got 100% Council Tax Benefit, suddenly had to pay a whopping 22% (this figure is from memory and applies (I’m massively simplifying here as there are people who don’t have to pay Council Tax too) to households of people of working age with nobody of state pension age and above). This led to an increase in people not paying, which led naturally to an increase in Magistrates’ Court cases filed by Wirral Council.

The Magistrates’ Court is of course where my father used to work before he retired and located just off Hamilton Square in Birkenhead and Tranmere ward, which by sheer coincidence is the ward where Wirral Council’s Leader of the Council/Cabinet Member for Finance Cllr Phil Davies represents.

At the time this change was planned and going out to consultation I warned Wirral Council in public meetings that this would need to lead to an increase in bad debt provision and their own costs!

Council Tax is one of the few taxes you can get locked up for in this country for not paying. Thus returning us to the concept of the “debtors prison” in Victorian England.

However the question is, how many people who literally couldn’t pay Council Tax, even if Wirral Council got a court order is Wirral Council going to the trouble of launching criminal cases over that costs the taxpayer money?

Bear in mind that this is a monthly invoice. Although the statement is in the name of LM Burns, it does somewhat remind me of the character of Charles Montgomery Burns in the Simpsons or as he would say “Release The Hounds!”

This is the court fee element, Wirral Council add this, plus their own internal legal costs to the outstanding Council Tax bill, which means by the end the Council Tax bill that they couldn’t pay before is even larger! Oh and thanks to Wirral Council, those who couldn’t pay end up at the end of the process with a criminal record, making it harder for them to get certain jobs to pay off their Council Tax debt!

Council Tax court cases Barclaycard invoice Wirral Council November 2013
Council Tax court cases Barclaycard invoice Wirral Council November 2013

If you click on any of these buttons below, you’ll be doing me a favour by sharing this article with other people. Thanks:

4 week consultation on closure of Lyndale School starts: does Wirral Council really know how many pupils are there?

4 week consultation on closure of Lyndale School starts: does Wirral Council really know how many pupils are there?

4 week consultation on closure of Lyndale School starts: does Wirral Council really know how many pupils are there?

                                                                  

Councillor Phil Gilchrist explains his amendment on the minority report on Lyndale School to councillors, officers and the public 2nd October 2014 Council Chamber, Wallasey Town Hall (c) John Brace
Councillor Phil Gilchrist explains his amendment on the minority report on Lyndale School to councillors, officers and the public 20th October 2014 Council Chamber, Wallasey Town Hall (c) John Brace

Following the Council meeting on the 20th October 2014 when Labour councillors voted to go ahead to the next stage on closure of Lyndale School, Wirral Council started on the 22nd October 2014 its four-week consultation on closure which finishes on 19th November 2014. After this consultation is finished, the results of this consultation will be reported back to Wirral Council’s Cabinet.

Proposal to cease to maintain the Lyndale School

Complete Proposal

You can also ask for copies of the proposals by calling 0151 606 2020 during office hours or writing to:

Julia Hassall
Director of Children’s Services
Hamilton Building
Conway Street
Birkenhead
CH41 4FD

The above files I’ve linked to are the new files in this current consultation.

You can respond to the consultation in one of two ways, either by email to specialreview@wirral.gov.uk or by mail to:

Julia Hassall
Director of Children’s Services
Hamilton Building
Conway Street
Birkenhead
CH41 4FD

I am unsure at this stage which Cabinet meeting the outcome of this four-week consultation on the closure of Lyndale School will go to. At the time of writing the following Cabinet meetings are scheduled for after the end of the consultation:

27th November 2014 | Special Meeting, Cabinet | Committee Room 1 – Wallasey Town Hall | starting at 6.15pm
9th December 2014 | Cabinet | Committee Room 1 – Wallasey Town Hall | starting at 6.15pm

Personally as the 27th November is a special meeting and occurs exactly one week and a day after the consultation ends, I would guess that this will be the public meeting at which the outcome of the second consultation and a further decision will be made. As agendas and reports have to be published at least a week before holding a Cabinet meeting, 27th November 2014 would be the earliest date it could be held.

However if this matter is called in after the Cabinet decision after the consultation and there are more delays in the process taking it past February 2015, it would make setting the 2015-16 Schools Budget problematic.

The reason is that if a final decision on closure is not made before February 2015, a contingency of funding Lyndale School from the proposed date of closure (January 1st 2016) to the end of that financial year (March 2016) would have to be added to the schools budget for 2015-16 of ~£140,000.

There are legal limits on when the 2015-16 Schools Budget has to be decided by and as there were delays earlier this year, I can see the next stages moving as fast as is humanly possible at Wirral Council (which when you do things as fast as you possibly can inevitably leads to mistakes).

However I would like to point out that the current consultation has at least one contradictory fact in Surjit Tour’s letter to me of the 30th September 2014 (although Mr. Tour obviously has to rely on what he’s told and take it at face value as I seriously doubt (although I could of course be wrong) that Mr. Tour visited Lyndale School and started asking children how old they are). I’ll explain what I mean (with references):

Here is the 13 page response from Mr. Tour. In it he states:

“8. Background

8.1 Lyndale School is a special school providing specialist educational provision for primary aged pupils, the majority of whom have Profound and Multiple Learning Difficulties (“PMLD”). There are 21 pupils currently on the roll, nine of whom will be transitioning to secondary school by the end of the 2015/16 academic year. The declining number of students admitted to Lyndale over recent years has drawn into question The Lyndale’s financial viability for the future.”

When I read Surjit Tour’s reply a few weeks ago, I thought it a bit odd that out of the eight year groups at Lyndale School, that almost half the school (nine out of twenty-one) would be in the final year and therefore leave to secondary school in September 2015 and not be affected by the proposals to close it. It seemed unusual at the time.

Mr. Tour repeatedly states throughout his letter that I have not provided evidence of my facts. However the evidence that proves him wrong on this was in fact published by Wirral Council on the 22nd October 2014 as part of the current consultation. Here is the table published as part of the Complete Proposal. The table is Pupil admissions and numbers.

F1 F2 Y1 Y2 Y3 Y4 Y5 Y6 Total
October
2014

Boys
Girls

3

2
1

1

0
1

3

1
2

2

2
0

3

3
0

1

1
0

6

2
4

2

1
1

21

12
9

December
2015

Boys
Girls

0



3

2
1

1

0
1

3

1
2

2

2
0

3

3
0

1

1
0

6

2
4

19

11
8

Number in each year group in December 2015 assumes that all current pupils remain on roll, that no new children are admitted to F1 (Nursery) in September 2015, and that no further children join or leave other year groups from October 2014 onwards.

As you can see from the table above there are two children (one boy and one girl) in year 6 at Lyndale School who will start at a secondary school in September 2015, not nine as claimed by Surjit Tour in his letter.

This then has an effect on other numbers used in his letter.

According to Surjit Tour 21-9 = 12 (twelve pupils left in September 2015)
According to Julia Hassall 21-2 = 19 (nineteen pupils left in September 2015)

So who do I trust to give the correct figure for pupils at the Lyndale School? The Head of Legal and Member Services (Surjit Tour) or the Director of Children’s Services (Julia Hassall)? They can’t both be right, can they?

On the balance of probabilities because:

a) Julia Hassall actually works in the area of Wirral Council with responsibility for schools
b) that it seems highly unlikely that nine of the twenty-one pupils at Lyndale School (spanning eight year groups) would be in the last year group

I’m veering towards believing Ms Hassall (although I never really relish taking sides when two people in Wirral Council’s senior management team are giving out contradictory information).

There is also the point that someone could have misread the table above and used the total number of girls presently at the school (nine) instead of the number of pupils in year six (two) and given that information to Surjit Tour to use in his letter.

Isn’t it weird though that when Wirral Council makes a mistake like this, it always coincides with their world view of a “small school” (in this case seven pupils less than it actually is)?

If Wirral Council can’t get basic facts such as how many pupils of what age are at Lyndale School right, is it any wonder that there are problems of trust between those associated with Lyndale School and Wirral Council?

If you click on any of these buttons below, you’ll be doing me a favour by sharing this article with other people. Thanks: